S.N. | Name of Infrastructure | Not Yet Started | Completed up to Plinth Level | Completed up to Lintel Level | Completed up to Roof Level | Totally Completed | Plinth area (sq.m) | Under use or not* | Source of Funding |
---|---|---|---|---|---|---|---|---|---|
1 | Administrative Building | Incomplete | ICAR | ||||||
2 | Farmers Hostel | Incomplete | ICAR | ||||||
3 | Staff Quarters (6) | Incomplete | ICAR | ||||||
4 | Piggery Unit | Not Started | ICAR | ||||||
5 | Fencing | Incomplete | ICAR | ||||||
6 | Rain Water Harvesting Structure | Not Started | ICAR | ||||||
7 | Threshing Floor | Completed | ICAR | ||||||
8 | Farm Godown | Incomplete | ICAR | ||||||
9 | Dairy Unit | ICAR | |||||||
10 | Poultry Unit | ICAR | |||||||
11 | Goatary Unit | ICAR | |||||||
12 | Mushroom Lab | ICAR | |||||||
13 | Mushroom Production Unit | ICAR | |||||||
14 | Shade House | ICAR | |||||||
15 | Soil Test Lab | ICAR | |||||||
16 | Fish Hatchery | Completed | District Adminstration |